RTS Link now targeted for February 2027: what agents near Bukit Chagar should know

Regional Market Trends · Johor · 2 Oct 2026 · By Property Connect Editorial

Infrastructure is substantially complete. Passenger service depends on final tests by 31 December 2026, independent safety certification and approvals from both countries.

English | 繁體中文

RTS Link now targeted for February 2027: what agents near Bukit Chagar should know
Photo: Seloloving / Wikimedia Commons, CC BY-SA 4.0, cropped

The new timeline

On 2 October 2026 Singapore's Land Transport Authority (LTA) and Malaysia's Ministry of Transport said the operator, RTS Operations (RTSO), now expects passenger service on the Johor Bahru–Singapore RTS Link to begin in February 2027.

  • Infrastructure works in both countries are substantially complete.
  • RTSO expects to finish its final system tests and trial runs by 31 December 2026.
  • It then needs certification from an independent safety assessor, followed by approvals from both governments.

Transport Minister Anthony Loke said on 8 October that the project is not delayed. Service could start as early as January, but February leaves a buffer for the safety evaluation and approvals. The opening date will be announced once APAD and the LTA have given all approvals.

The line in numbers

ItemDetail
RouteBukit Chagar (Johor Bahru) to Woodlands North (Singapore), about 4 km
JourneyAbout 5 minutes
CapacityUp to 10,000 passengers per hour each way
ImmigrationCo-located: clear both countries at the station where you board
Singapore connectionThomson–East Coast MRT line at Woodlands North
FareNot announced yet

Asking rents near the station

Asking rents published by local agents and developers in late 2026 for completed freehold condos within walking distance of Bukit Chagar:

CondoApprox. distanceAsking rent (RM a month)
TriTower Residence220–350 mStudio about 2,740; 2-bed about 3,075; 3-bed about 4,550
SKS Pavillion Residences450–600 mStudio 2,000–2,300; 2-bed 2,500–2,800
R&F Princess Cove (Phase 1)About 700 mStudio 2,100–2,800; 2-bed 2,700–3,000
Twin Tower ResidenceAbout 700 mStudio 2,600–3,000; 2-bed 3,300–3,600

These are asking figures from marketing sites, not transacted rents.

Practical advice

  • The market pays for walking distance. Measure the actual walking route to the station, not the straight line.
  • Much of the RTS story is already in asking prices. Before a buyer makes an offer, compare with the NAPIC transacted prices on Property Connect.
  • A feeder rail line has been discussed for Johor Bahru, but no routes, stations or completion date had been confirmed as of October 2026. Do not charge a premium for being "on a future feeder line".

Sources