Developers & launches · 2026-11-26
An automatic cut of 5 property-related headlines for agents, refreshed through the day.
Read the articleInfrastructure is substantially complete. Passenger service depends on final tests by 31 December 2026, independent safety certification and approvals from both countries.
English | 繁體中文

On 2 October 2026 Singapore's Land Transport Authority (LTA) and Malaysia's Ministry of Transport said the operator, RTS Operations (RTSO), now expects passenger service on the Johor Bahru–Singapore RTS Link to begin in February 2027.
Transport Minister Anthony Loke said on 8 October that the project is not delayed. Service could start as early as January, but February leaves a buffer for the safety evaluation and approvals. The opening date will be announced once APAD and the LTA have given all approvals.
| Item | Detail |
|---|---|
| Route | Bukit Chagar (Johor Bahru) to Woodlands North (Singapore), about 4 km |
| Journey | About 5 minutes |
| Capacity | Up to 10,000 passengers per hour each way |
| Immigration | Co-located: clear both countries at the station where you board |
| Singapore connection | Thomson–East Coast MRT line at Woodlands North |
| Fare | Not announced yet |
Asking rents published by local agents and developers in late 2026 for completed freehold condos within walking distance of Bukit Chagar:
| Condo | Approx. distance | Asking rent (RM a month) |
|---|---|---|
| TriTower Residence | 220–350 m | Studio about 2,740; 2-bed about 3,075; 3-bed about 4,550 |
| SKS Pavillion Residences | 450–600 m | Studio 2,000–2,300; 2-bed 2,500–2,800 |
| R&F Princess Cove (Phase 1) | About 700 m | Studio 2,100–2,800; 2-bed 2,700–3,000 |
| Twin Tower Residence | About 700 m | Studio 2,600–3,000; 2-bed 3,300–3,600 |
These are asking figures from marketing sites, not transacted rents.