Regional Market Trends

Malaysia's data centre wave, November 2026: new projects, new power rules and what they mean for property

Regional Market Trends · Nationwide · 11 Nov 2026 · By Property Connect Editorial

Google, SoftBank–Grab–PETROS and a string of hyperscale construction contracts in one month, while new approvals now require off-grid power, 30% renewable energy and two days of water storage.

English | 繁體中文

Malaysia's data centre wave, November 2026: new projects, new power rules and what they mean for pro
Photo: CharlieMehta / Wikimedia Commons, CC BY-SA 4.0, cropped

The numbers

  • Johor, first half of 2026 (Cushman & Wakefield): 1,110 MW operational, up 24% from the second half of 2025; 602 MW under construction; 2,486 MW planned. Colocation vacancy was 0.7%, so new capacity is taken up almost immediately.
  • Malaysia leads Southeast Asia with 1,039 MW under construction.
  • Electricity: contracted demand from data centres was 2,346 MW in August 2026, but actual use was 1,374 MW, or 58.5% (Deputy Prime Minister Fadillah Yusof, 28 October).
  • Pipeline: the Data Centre Task Force received more than 40 new applications in 2026 (The Star).

New rules for new data centres

  • Off-grid power: letters of award for fewer than 30 newly approved projects, about 8 GW combined, reportedly require developers to secure their own "off-grid" power, either by building plants or by buying from dedicated or captive power producers (The Star, 19 October).
  • Renewable energy: at least 30% of each operator's energy must be renewable. The Energy Commission is drafting the framework, and operators are encouraged to use the Corporate Renewable Energy Supply Scheme (CRESS) and Solar for Self-Consumption (SELCO).
  • Water and backup: data centres must keep at least two days of water on site and have backup generators, which can be used to reduce demand when grid reserves are low (New Straits Times).
  • Johor also applies its own water-efficiency limit; see Microsoft's Johor Bahru cloud region, and Johor's water rules.

The latest announcements

DateWhoWhatWhere
4 NovGoogleUS$15 billion for 2027–2028; first campus at Elmina now live, new campuses plannedSelangor, Negeri Sembilan
5 NovSunway ConstructionRM1.74 billion core, shell and MEP contract from an international hyperscaler, Q4 2026 to Q4 2028Bandar Serendah, Selangor
5 NovMicrosoftUpdate on the Southeast Asia 3 cloud region, its largest planned in the regionJohor Bahru
9 NovSoftBank, Grab, PETROSUS$1.85 billion of seed capital (Sarawak US$1 billion, Peninsular Malaysia US$850 million), long-term target of 5 GW or moreSarawak, Peninsular Malaysia
10 NovJati TinggiRM33.1 million of 275 kV power works for a data centreGerbil, Negeri Sembilan

Earlier in the half: Tencent Cloud opened its first Malaysian cloud region in Johor (18 August), and YTL Power announced a second gigawatt campus at Sedenak Tech Park West (19 August). The Bandar Serendah job was Sunway Construction's seventh data-centre-related contract of 2026, taking its new orders for the year to RM9.8 billion; days earlier it also received a RM920.8 million variation order for MEP works at a Johor data centre for a US technology company.

What it means for property

  • Power beats land. Sites near gas pipelines, main intake substations and transmission lines, and states with spare generation such as Sarawak, gain the most. Land bought for data centres without a power plan may be delayed or resold.
  • Construction towns. Two-year build programmes bring engineers and workers who need rooms, apartments and workers' quarters near Bandar Serendah and Rawang, Elmina, Kulai–Sedenak and the Negeri Sembilan sites.
  • Read the headlines carefully. Announced capacity is not built capacity: approvals now depend on securing power, and contracted electricity use is running at only 58.5% of what was booked. Sell a location on what has started construction, not on what has been announced.