Penang's Mutiara LRT reaches 16% as the RM2.69 billion sea-crossing contract is awarded

Regional Market Trends · Penang · 5 Nov 2026 · By Property Connect Editorial

MRT Corp awarded the 5.5 km Macallum–Penang Sentral link, including a 3.05 km bridge. Komtar to Penang Sentral will take about eight minutes.

English | 繁體中文

Penang's Mutiara LRT reaches 16% as the RM2.69 billion sea-crossing contract is awarded
Photo: HundenvonPenang / Wikimedia Commons, CC BY-SA 4.0, cropped

The contract

On 5 November 2026 MRT Corp awarded Civil Main Contract 2 (CMC2) of the Mutiara Line, worth RM2.69 billion, to a joint venture of China Communications Construction Company, TRC Construction and Ufuk Semarak.

  • Route: about 5.5 km from Macallum on the island to Penang Sentral in Butterworth.
  • Bridge: a 3.05 km sea crossing with navigation spans for ships using the Prai and Butterworth ports, plus an elevated station.
  • Journey: Komtar to Penang Sentral in about eight minutes, with connections to KTM trains, ferries and buses.
  • Term: five years, according to TRC Synergy's filing to Bursa Malaysia.

In August, MRT Corp awarded the RM3.03 billion railway systems contract to a joint venture of MRCB and Theta Edge.

Progress

  • Whole line: 16% complete and on schedule (MRT Corp, 5 November).
  • First package, Komtar to Silicon Island (23.7 km): 15.5% complete at the end of September 2026, Chief Minister Chow Kon Yeow said when tabling Penang's Budget 2027 on 30 October.
  • The line: 29.67 km with 20 stations and two provisional stations under the railway scheme published in February 2026. The Transport Ministry put the cost at RM16.8 billion in June.
  • Timing: main construction of the sea crossing starts in the third quarter of 2027 after preliminary works, and passenger service is targeted for December 2031 (as reported by Industrial and Land).

What it means for property

  • The sea link turns Penang Sentral into an interchange for island-bound commuters from Butterworth, Bukit Mertajam and Batu Kawan. Areas within walking distance of the mainland stations gain the most.
  • The draft Sungai Nibong transit-oriented development master plan, prepared with the Asian Development Bank, is due by the end of 2026.
  • Service is about five years away. Value a home on today's access and treat the LRT as a long-term bonus. Expect traffic diversions along the alignment during construction.